9 Replies Latest reply on Jul 12, 2018 8:55 AM by David Leventhal

    Ganntt chart - I want to show % complete progess on each duration bar

    Michelle Church

      I am working on a report that shows all the tasks on a number of projects.  I am doing it as a Ganntt chart type with the start date and bar length is derived from the duration of the task.  I want to show a darker shading on the bar to indicate the % complete of the task.  Right now I have only been able to figure out how to get the % complete to be represented by different colors.  I am including a twbx file to show what I have so far and also a picture called Ganntt Chart example to show what it is I am hoping to do with the progress showing on the bars.  Does anyone know how to do this?  I have googled it a ton and can't find anything.